MEPFP enabling Bldg 4, 10, 13, 16, 26
this steps is for them to get ready to plan out the work days -
Bldg. 26 installation of heat trace away
-
Bldg. 26 pile install for new loading dock & area way
-
Eastman Court - excavation and back fill at MH M37. This they want to refill a hole or something. Something that got dung out.
-
Installation of FP main connection between Bldg. 24 and 26. And FP stands Fire Protection and the number represent the block or wall number of building.
-
Insulate temp. FP/ fire protection line at Bldg. 13 Arcade. Which means to rap the pipes up for cool temp. in the winter time/ season.
-
Test pits to verfiy exsiting utlities tp prepare for new the chill water/ CHW lines. Meaning the hot lines and the cool water lines.
-
Prepare sub grade for paving on a specific road/highway when necessary .
-
They will start to clean the road to brush off the ass-fault on the road to make it a soft ride to your destination.
-
Next we will be removing old gas pipes/lines in the ground to replace them with new ones so the can run good.
-
First what we gonna do is dig out the pipes and all around then then we want to start cutting them in sections so it want be a lot of weight on one truck.
-
The next thing is we are gonna have to order the new pipes and get dozier/cranes to level them down in the dirt.
-
We got the pipes in today so we are gonna start putting/laying down the pipe where they are supposed to be.
-
we will cover them with dirt and cement around them to make sure they stay in tact. Then we run the fluid through the pipes to mkae sure no leeks.
-
The final day we make sure every thing is packed up a ready to be loaded onto the trucks and make sure everything is working properly.