Solyndra Loan Guarantee Time Line

  • Global silicon shortage begins to drive up prices of solar photovoltaicis

  • Bush Administration signs Energy Policy Act of 2005 into law creating 1703 loan guarantee program

  • Period: to

    Solyndra raises its first round of venture financing

    worth $10.6 million from CMEA Capital, Redpoint Ventures, and U.S. Venture Partners. In October, Argonaut Venture Capital, an investment arm of George Kaiser, invests $17 million into Solyndra. Madrone Capital Partners, an investment arm of the Walton family, invests $7 million. Those investments are part of a $78.2 million fund.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • Solyndra Applies for Loan Guarantee under 1703 program

  • Loan guarantee program is funded

    Think progress say's "Late 2007"
  • Solyndra CEO Chris Gronet touted reasons for building in Silicon Valley

    noted that the “company’s second factory also will be built in Fremont, since a Department of Energy loan guarantee mandates a U.S. location.”
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • Silicon prices remain very high on the spot market

    making non-silicon based thin film technologies like Solyndra’s very attractive to investors. Solyndra also benefits from having very low installation costs. The company raises $144 million from ten different venture investors, including the Walton-family run Madrone Capital Partners. This brings total private investment to more than $450 million to date.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • Bush Administration tries to take Solyndra before a DOE credit review committee before President Obama is inaugurated.

    In an effort to show it has done something to support renewable energy, the Bush Administration tries to take Solyndra before a DOE credit review committee before President Obama is inaugurated. The committee, consisting of career civil servants with financial expertise, remands the loan back to DOE “without prejudice” because it wasn’t ready for conditional commitment.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • The same credit committee approves the strengthened loan application.

    The same credit committee approves the strengthened loan application. The deal passes on to DOE’s credit review board. Career staff (not political appointees) within the DOE issue a conditional commitment setting out terms for a guarantee.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • Silicon prices start to drop

    As more silicon production facilities come online while demand for PV wavers due to the economic slowdown, silicon prices start to drop. Meanwhile, the Chinese begin rapidly scaling domestic manufacturing and set a path toward dramatic, unforeseen cost reductions in PV. Between June of 2009 and August of 2011, PV prices drop more than 50%.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • Solyndra raises an additional $219 million.

    Solyndra raises an additional $219 million. Shortly after, the DOE closes a $535 million loan guarantee after six months of due diligence. This is the first loan guarantee issued under the 1703 program. From application to closing, the process took three years – not the 41 days that is sometimes reported. OMB did raise some concerns in August not about the loan itself but how the loan should be “scored.” OMB testified Wednesday that they were comfortable with the final scoring.
    http://thinkp
  • Period: to

    price of conventional silicon-based PV continues to fall due to low silicon prices

    As the price of conventional silicon-based PV continues to fall due to low silicon prices and a glut of solar modules, investors and analysts start questioning Solyndra’s ability to compete in the marketplace. Despite pulling its IPO (as dozens of companies did in 2010), Solyndra raises an additional $175 million from investors.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • Solyndra closes an older manufacturing facility and concentrates operations at Fab 2

    Solyndra closes an older manufacturing facility and concentrates operations at Fab 2, the plant funded by the $535 million loan guarantee. The Fab 2 plant is completed that same month — on time and on budget — employing around 3,000 construction workers during the build-out, just as the DOE projected.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • Due to a liquidity crisis, investors provide $75 million to help restructure the loan guarantee.

    Due to a liquidity crisis, investors provide $75 million to help restructure the loan guarantee. The DOE rightly assumed it was better to give Solyndra a fighting chance rather than liquidate the company – which was a going concern – for market value, which would have guaranteed significant losses.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • Republican Representatives complain that DOE funds are not being spent quickly enough.

    House Energy and Commerce Committee Chairman Fred Upton (R-MI): “despite the Administration’s urgency and haste to pass the bill [the American Recovery and Reinvestment Act] … billions of dollars have yet to be spent.” And House Oversight and Investigations Subcommittee Chairman Cliff Stearns (R-FL): “The whole point of the Democrat’s stimulus bill was to spend billions of dollars … most of the money still hasn’t been spent.”
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-admini
  • Average selling prices for solar modules drop to $1.50 a watt and continue on a pathway to $1 a watt.

    Average selling prices for solar modules drop to $1.50 a watt and continue on a pathway to $1 a watt. Solyndra says it has cut costs by 50%, but analysts worry how the company will compete with the dramatic changes in conventional PV.
    http://thinkprogress.org/romm/2011/09/13/317594/timeline-bush-administration-solyndra-loan-guarantee
  • DOE refuses to restructure the loan a second time.

  • Solyndra closes its manufacturing facility, lays off 1,100 workers and files for bankruptcy.

    The news is touted as a failure of the Obama Administration and the loan guarantee office. However, as of September 12, the DOE loan programs office closed or issued conditional commitments of $37.8 billion to projects around the country. The $535 million loan is only 1.3% of DOE’s loan portfolio. To date, Solyndra is the only loan that’s known to be troubled. Meanwhile, after complaining about stimulus funds moving too slowly, Congressmen Fred Upton and Cliff Stearns are now claiming that the