Instruct the trainee on what to do and how to do it.
-
Do this 2-3 months in advance!
-
Do this 2-3 months in advance. Confirm delivery dates and schedule installation and construction for hardware.
-
The hotel personell provides vendor with the necessary information to build the database 1-2 months in advance.
-
Verify the conversion date and make final installation arrangements one month in advance.
-
Check that equipment arrives, forms and supplies are received, training room is set up, and install and test hardware 2-4 weeks in advance.
-
This is done 2 weeks prior to installation. It will consist of scheduling reservations personnel, making consistent hours according to department, and preparing a master training schedule.
-
This meeting should train employees on what to expect within the first 3 months.
-
After night audit, the system goes live after guest folio and city ledger balances are transferred to the new system.
-
Vendor trainers monitor system and assist employees.
-
The vendor representative will assist the PMS coordinator on implementation problems until acceptance criteria are satisfied.