    Contract Timeline

  • Contract Solicitation Cancelled - HSFELA-09-D-0072

    the requirement will be fulfilled under current contract
  • Contract HSFEEM-09-C-0412 Awarded

    Amount: $7,912,420.00
    CLIN1 - $7,444,209.52
    CLIN2 - $91,428.57
    CLIN3 - $376,781.91
    Scope: 8 buildings
    COTR: Perry Joy
    Completion Date: 09/30/2010
  • MOD P00001 Signed

    Issued to cover additional design and testing services not anticipated
    Amount: $7,912,420.00 - no change
    CLIN1 - $7,294,209.52 - decreased $150K
    CLIN2 - $241,428.57 - increased $150K
    CLIN3 - $376,781.91
    Scope: no change
    COTR: no change
    Completion Date: no change
  • MOD P00002 Signed

    Issued to change P&P bond from 5% of the original contract price to 100% of the original contract price
    Amount: no change
    Scope: no change
    COTR: no change
    Completion Date: no change
  • COTR Change: from JOY to BENSON

  • MOD P00003 Signed

    Issued to change completion date to 5/18/2011 and update wage scale
    Amount: no change
    Scope: no change
    COTR: no change
    Completion Date: 05/18/2011
  • MOD P00004 Signed

    Issued to incoporate by reference FAR Clause 52.242-15, Stop Work Order, ALT 1 (Aug 1989) to section 1 of contract
    Amount: no change
    Scope: no change
    COTR: no change
    Completion Date: no change
  • MOD P0005 Signed

    issued to change COTR from Valerie Benson to Barry Thoma
    Amount: no change
    Scope: no change
    COTR: Barry Thoma
    Completion Date: no change
  • COTR changed from BENSON to B. THOMA

  • MOD P00006 Signed

    Issued to incorporate Phase 1 (building F) specifications and drawings into this contract. Drawings located on GMI FTP site. Phase 1 work is complete
  • Increase Funding Request

    Increase funding request of $1,059,547.57 based on revised scope
    extend completion date to 11/15/2011