Contract Timeline
-
Contract Solicitation Cancelled - HSFELA-09-D-0072
the requirement will be fulfilled under current contract -
Contract HSFEEM-09-C-0412 Awarded
Amount: $7,912,420.00
CLIN1 - $7,444,209.52
CLIN2 - $91,428.57
CLIN3 - $376,781.91
Scope: 8 buildings
COTR: Perry Joy
Completion Date: 09/30/2010 -
MOD P00001 Signed
Issued to cover additional design and testing services not anticipated
Amount: $7,912,420.00 - no change
CLIN1 - $7,294,209.52 - decreased $150K
CLIN2 - $241,428.57 - increased $150K
CLIN3 - $376,781.91
Scope: no change
COTR: no change
Completion Date: no change -
MOD P00002 Signed
Issued to change P&P bond from 5% of the original contract price to 100% of the original contract price
Amount: no change
Scope: no change
COTR: no change
Completion Date: no change -
COTR Change: from JOY to BENSON
-
MOD P00003 Signed
Issued to change completion date to 5/18/2011 and update wage scale
Amount: no change
Scope: no change
COTR: no change
Completion Date: 05/18/2011 -
MOD P00004 Signed
Issued to incoporate by reference FAR Clause 52.242-15, Stop Work Order, ALT 1 (Aug 1989) to section 1 of contract
Amount: no change
Scope: no change
COTR: no change
Completion Date: no change -
MOD P0005 Signed
issued to change COTR from Valerie Benson to Barry Thoma
Amount: no change
Scope: no change
COTR: Barry Thoma
Completion Date: no change -
COTR changed from BENSON to B. THOMA
-
MOD P00006 Signed
Issued to incorporate Phase 1 (building F) specifications and drawings into this contract. Drawings located on GMI FTP site. Phase 1 work is complete -
Increase Funding Request
Increase funding request of $1,059,547.57 based on revised scope
extend completion date to 11/15/2011