  • CAT increase 100-3878

    CAT created a collaboration for increasing the quantity to ship on June 4th 1,200 pcs (460 kg) (expedited at their cost)
  • 100-3878 Quality issue internal detection

    Material rejection due to oxide detection in the warehouse for 1,951 pcs (750 kg)
  • 100-3878 Quality issue detected in CAT

    2,424 pcs (900kg) scrapped in Lafayette due to oxide material detected.
  • CAT increase 100-3878

    CAT created a collaboration for increasing the quantity to ship on August 7th 1,500 pcs (600 kg) (expedited at their cost)
  • PO 3630325 placed on 9/17

    order placed to Garph Japan for deliver 5k kg on 11/01
  • PO 3630326 placed on 9/17

    order placed for deliver 7k kg on 1/01/2021
  • CAT increase 100-3878

    CAT created a collaboration for increasing the quantity to ship on Sep th 1,400 pcs (535 kg) (expedited at their cost)
  • SG Acknoledgment

    Danie from SG confirmed the material of the 2 POs would be ready to deliver until January, but will be pushing for improving the delivery date
  • Japan’s lead time continues to extend

    Danie from SG suggested issuing POs for any March&April 2021 requirements we may have.
  • April 2021 orders placed.

    Hi Danie,
    our needs for April 2021 will be for the following: RM033S-189-50I 4,000 lbs
    RM033S-296-50I 4,000 lbs
    RM033S-306-00I 16,000 lbs
  • SG re-confirmed the material was going to be ready on Japan in 12/21

    12/21 is the date they confirmed material will be ready to ship
  • RM033S-306-00I quote for expediting requested (not an option)

    air freight for 900kg was quoted for $25,000 usd
  • PO 3630325 arrival date

    5,282 kg arrived on 1/08/2021
  • PO 3630326 arrival date

    7,000 kg arrived on 1/18