Construction Process of Lamma Winds By Stephaniexixi Apr 29, 2001 A year-long wind monitoring studies begins Apr 5, 2003 Site Evaluations and Selection are carried out Mar 1, 2004 Environmental impact assessment confirms that Tai Ling is the most desirable location for a wind turbine Nov 1, 2004 HK Electric receives environmental permit from the government Feb 1, 2005 Site information and civil work begins on the site Aug 1, 2005 Equipmens arrive from Germany Sep 1, 2005 Equipment is transported to the top of Tai Ling Oct 1, 2005 Fuction testing, construction of exhibition centre, road works and landscaping Feb 1, 2006 Commissioning of wind power station