CRONOGRAMA REAL By facebooker_3679207215491113 Period: Oct 15, 2020 to Oct 30, 2020 LIMPEZA DA OBRA E INSTALAÇÕES DE CANTEIRO Nov 3, 2020 INICIO DA OBRA NO PRAZO CONTRATUAL Period: Nov 3, 2020 to Nov 11, 2020 DEMOLIÇÃO DO MURO E DESLOCAMENTO DO TAPUME Period: Nov 12, 2020 to Nov 17, 2020 GABARITO Period: Nov 18, 2020 to Nov 19, 2020 MARCAÇÃO DO GABARITO Period: Nov 24, 2020 to Dec 11, 2020 EXECUÇÃO DAS ESTACAS ETAPA 1 Period: Dec 15, 2020 to Jan 12, 2021 EXECUÇÃO DOS BLOCOS PARA LIBERAR TRANSPLANTE DAS ÁRVORES Period: Jan 15, 2021 to Jan 19, 2021 TRANSPLANTE DAS ÁRVORES Period: Jan 20, 2021 to Feb 1, 2021 CRAVAÇÃO DOS PERFIS Period: Feb 4, 2021 to Feb 11, 2021 EXECUÇÃO DAS ESTACAS ETAPA 2 Period: Feb 12, 2021 to Mar 12, 2021 ESCAVAÇÃO E PLAQUEAMENTO Period: Mar 12, 2021 to Apr 29, 2021 BLOCOS E BALDRAMES