April: The running track is due to be laid in the main stadium
-
Autumn 2011 – Construction finishes on athletes village which is handed over to LOCOG
-
September 2011 - Westfield Stratford shopping centre due to open
-
December 2011: Media centre construction complete
-
January: ODA handover of entire Olympic site to LOGOC
-
February: Royal Docks cable car goes into operation
-
May: Torch relay begins 70-day journey in Land's End, Cornwall
-
July 15: Official opening of Olympic Village
-
July 27: Olympic Games opening ceremony
-
August 12: Olympic Games closing ceremony
-
August 29: Paralympic Games opening ceremony
-
September 9: Paralympic Games closing ceremony
-
September 14: Olympic park closes for development work
-
September 16: Athletes village closes