YRMC Constrcution Project

  • Build out of the third and fifth Tower floors

    Construction started – September, 2012
    Expected completion – February, 2013
  • Heart Center of Yuma Hybrid Suite

    Construction started – September, 2012
    Expected completion – March, 2013
  • Interim Emergency Department

    Construction started – October, 2012
    Expected completion – January, 2013
  • Yuma Regional Cancer Center

    Estimated construction start – May, 2013
    Expected completion – March, 2014
  • Emergency Department

    Estimated construction start – June, 2015
    Expected completion – September, 2016