Year 9 Maths House Construction

By Raltexe
  • Construction Starts

    The house starts to be built!
  • Period: to

    Preparing site: 2 weeks

  • Period: to

    Plumbing: 3 days

  • Period: to

    Slab: 2 days

  • Period: to

    Frame: 4 weeks

  • Period: to

    Windows: 2 days

  • Period: to

    Roof: 3 days

  • Period: to

    Cladding frame: 1 week

  • Period: to

    Electrical: 8 hours

    8 hours is about an average working day for a builder so this is counted as one days work.
  • Period: to

    Internal wall lining: 4 days

  • Period: to

    Waterproofing: 1 day

  • Period: to

    Tiling wet areas: 5 days

  • Period: to

    Fixtures and fittings: 3 days

  • Period: to

    Flooring timber: 6 hours

    This will be done within the day so it is one days work.
  • Period: to

    Carpets: 8 hours

    This is one whole days work.
  • Period: to

    Painting Internally: 8 days

  • Period: to

    Painting Externally: 6 days

  • Period: to

    Landscaping and driveway: 5 days

  • Period: to

    Fence: 3 days

  • Construction Finishes

    The house is done!