Day1
Arrive. Contact Manifacturing ompany. Contact village leaders. Rent trucks. Load. -
Period: to
Project Timeline
-
Day 2-5
Head out to villages. Group 1: Kasaligu Group 2: Taha
Meet with village leader and two locals. choosee location. set-up assembly. insturction to locals. begin drilling. disassemble. store -
Day 6
return to villages. check-up. help with any problems. -
Day 7-9
Head out to villages. Group 1: Nyamaliga Group 2: Bahalahi
Meet with village leader and two locals. choosee location. set-up assembly. insturction to locals. begin drilling. disassemble. store -
Day 10
return to villages. check-up. help with any problems. -
Day 11-13
Head out to villages. Group 1: Jarigu Group 2: Bamvim
Meet with village leader and two locals. choosee location. set-up assembly. insturction to locals. begin drilling. disassemble. store -
Day 14
return to villages. check-up. help with any problems. -
Day 15-18
Head out to villages. Group 1: Nyesie Group 2: Giana
Meet with village leader and two locals. choosee location. set-up assembly. insturction to locals. begin drilling. disassemble. store -
Day 19
return to villages. check-up. help with any problems. -
Day 20-23
Head out to villages. Group 1: Giana Group 2: Tingoli
Meet with village leader and two locals. choosee location. set-up assembly. insturction to locals. begin drilling. disassemble. store -
Day 24
return to villages. check-up. help with any problems. -
Day 25-26
Talk to Village leaders. make sure all is in order. pack up return to America.