UNMAS N68 Grant Timeline

  • CFP Released by UNMAS

  • HALO Submits Proposal to UNMAS

  • UNMAS Awards Grant to HALO and Al Ghad

  • Period: to

    Grant Period

  • HALO Submits Mobilisation Report

    HALO Submits Mobilisation Report
    Report includes details of initial support training for Al Ghad and intention to hire and train operations staff in January and February, 2021.
  • First Milestone Report Submitted

    First Milestone Report Submitted
  • Operations Staff Recruitment

    Operations Staff Recruitment
    01 January - 31 January 2021
  • Operations Staff Training

    Operations Staff Training
    13 February - [15 April] 2021
    Basic Deminer Course
    Intermediate Care Provider
    NTS (for MTT)
    Mechanical Operator (for Mech team)
    Community Liaison
    EORE
  • CORE team deployed

    First deployment: Hay Alnuyamiah and Al-Karmah Delay in deployment due to delay receiving task order
  • Period: to

    Operations Ongoing

  • Second Milestone Report Submitted

    Second Milestone Report Submitted
  • Mech Team First Deployed to Minefield

    Mech Team First Deployed to Minefield
    First task: Hay Alnuyamiah (Cl-HALO-TRUST-160/21) Delay in deployment due to delay receiving task order
  • MTT Teams First Deployed

    First task: Hay Alemeen (Cl-HALO-TRUST-174/21) to support HALO's UNMAS-funded Fallujah survey team Delay in deployment due to delay receiving task order
  • Third Milestone Report Submitted

    Third Milestone Report Submitted
  • MTT and CORE Teams Restructured

    MTT and CORE Teams were restructured from 01 September - 25 November to reduce the predicted Year 1 underspend. They were restructured to create four NTS teams. UNMAS was made aware in the Fourth Milestone report and did not raise any objections.
  • Fourth Milestone Report Submitted

    Fourth Milestone Report Submitted
    UNMAS made aware of MTT restructure in this report. They did not raise any formal objection.
  • Fifth Milestone Report Submitted

    Fifth Milestone Report Submitted
  • First Submission of Budget Amendment

    First Submission of Budget Amendment
    This amendment covered the altered team structure: x2 Mech teams
    x2 MTTs
    x0 CORE team
  • Period: to

    HALO UNMAS Budget Amendment Correspondence

    This includes only formal correspondence (submission of budgets and formal requests for clarification/rejection of costs)
  • Sixth Milestone Report Submitted

    Sixth Milestone Report Submitted
  • Seventh Milestone Report Submitted

    Seventh Milestone Report Submitted
  • Amended Team Structure Formally Rejected by UNMAS

    Amended Team Structure Formally Rejected by UNMAS
  • Eighth Milestone Report Submitted

    Eighth Milestone Report Submitted
    Report was due 15 September, HALO request an extension to 20 September for financial reporting, but then financial report was not available until 26 September, so report was submitted on 27 September.
  • UNMAS Rejects HALO from bidding for Year 3

  • Budget Amendment Formally Rejected by UNMAS (Final)

  • Project Ends