The reactor was operating at 97% power and had a minor malfunction and caused the cooling circuit to rise
-
43,000 curies of krypton were vented from the reactor building
-
The first manned entry into the reactor building took place
-
An advisory Panel for the Decontaminatoin of TMI-2,composed of citizens,scientists,and state ,held meeting in Harrisburg,PA
-
the reactor vessel head was removed
-
Fuel removal began
-
the off-site shipment of reactor core debris began
-
GPU submitted a request for a proposal to amend the T MI-2 license to a "possession-only" license and to allow the facility to enter long-term monitoring storage.
-
Fuel removal was completed.
-
GPU submitted its funding plan for placing $229 million in escrow for radio logical decommissioning of the plant.