Reporting/File Feed Transition from DCS to THAA Checklist

  • Review Reports and File Feed Transition Strategy

    9 months prior to transition date
  • Meet with Customer to Talk about Transition

    8 months prior to transition
  • Submit Ticket for File Feed Work and NSR for any Report Customizations

    7 months prior to transition date
  • File Feed Work Begins - Customer and Hartford Resources Assigned to Implement

    6 months prior to transition date
  • Establish Standard On-Demand Report Deliver or other Options (TLS/MFT) - Submit Ticket as Appropriate for TLS/MFT Delivery Options

    5 months prior to transition date
  • Ensure any Custom Reporting Work is on Track to be Completed by go-Live Date

    2 months prior to transition date