MCM

  • Start of Construction

  • Beginning of Franklin and RMD Escalation Claim Period

  • Period: to

    Franklin Escalation Time Span

  • Original Construction Completion Date

  • NOPC 34 (first notice, without quantification)

  • Caltrans Acknowledged Extension from CCO 157 Memo

  • CCO 157 Issued

  • Caltrans Further Acknowledged Extension from CCO 157 Memo

  • Period: to

    Notes Say Review Delay Responsibility "Day by Day" During This Time

  • DG Construction Opinion (77 additional days beyond 11/2/04)

  • New Construction End Date Per CCO 157