Maths Assignment

  • Preparing Site

    Preparing the site takes 2 weeks.
  • Plumbing

    The plumbing takes 3 days
  • Slab

    The slab takes 2 days
  • Frame

    The frame takes 4 weeks.
  • Windows

    take 2 days
  • Roof

    3 days
  • Cladding Frame

    Cladding frame takes 1 week
  • Electrial

    Takes 8 hours.
  • Innternal Wall lining

    Takes 4 days
  • Waterproofng

    Takes 1 day
  • Tiling wet area's

    Takes 5 days
  • Fixtures and Fittings

    Takes 3 days
  • Timber floors

    Takes 6 hours
  • Carpets

    Takes 8 hours.
  • Painting internally

    Takes 8 days
  • Painting externally

    Takes 6 days
  • Lanscape and Driveway

    Takes 5 days
  • Fence

    Takes 3 days