La Bahn Arena

  • Enumeration

    The University of Wisconsin system approves a $27,787,000 Kohl Center Hockey Facility in the 2009-2011 budget.
  • Construction manager

    Wis. Stat. 16.885 authorizes the selection of a construction manager for the La Bahn Arena project.
  • Final Approval

    Wisconsin State Building Commission approves the final design report for La Bahn Arena.
  • Additonal costs

    Department of Administration adds $495,000 in gifts for additional costs for a revised project cost of $28,282,000.
  • Bid date

    Bid to Wisconsin State Building Commission for construction.
  • Board of Regents approval

    Board of Regents approves the budget and schedule for La Bahn Arena.
  • Project cost increase

    Board of Regents approves a $5,814,000 project cost increase for a new total cost of $34,096,000.
  • State Building Commission approval

    Wisconsin State Building Commission approves the budget and building schedule for La Bahn Arena.
  • Construction begins

    Construction begins on La Bahn Arena.
  • Groundbreaking ceremony

    Groundbreaking ceremony
    Groundbreaking ceremony held at the future site of La Bahn Arena.
  • Completion

    Completion
    La Bahn Arena is scheduled to open in October of 2012.