JMS OpenHR System Implementation Timeline

  • Period: to

    Project

  • Part 2 of OHR System Build

  • Part 3 of OHR System Build

  • Migration of Test Data to OHR

    Dianne King in all day to assist with Migration and config.
  • Phase 1 UAT Build Modifications (1)

    Day allocated for system modifications following initial testing of build. UAT being carried out by P1 users: MF, KM, LM. Simon Holmes from ABS will be undertaking this work with MF.
  • Lockdown of Monthly Maxcel Data

    COH - this affects TOC & KM
  • Data cut of Monthly Employee Records

    Tentative date for cut of monthly migration, Lockdown of monthly data entry fields in Maxcel. Preparation of data exported out of Maxcel Commences (COH & MF).
  • Interface Testing (3 days)

    Testing of interface
  • Tentative Stakeholder Meeting

  • Migration of Monthly Data to Live

    Greg from ABS in all day to assist with migration.
  • GO LIVE!

  • TBC: Data cut of weekly employee records

    Tentative date for cut of weekly migration, Lockdown of Weekly data entry fields in Maxcel. Preparation of data exported out of Maxcel Commences (COH & MF).
  • TBC: Weekly Employee Data Migration

    Tentative date for migration of weekly employee data.
  • TBC: Training Data Cut & Lockdown of Training Database

    Tentative date for extraction of training history from Murphy Online. Lockdown of MurphyOnline Training Database (preventing further entry/updates of records).
  • TBC: Migration of Training Records

    Tentative date for migration of training records.
  • TBC: HSQE Functionality

    O/H Data
    Hazard Spotter Data
    Incidents/Accidents Tracker