EXPANSION PROCESS (Amaya History) By juanarmas May 29, 2017 CAAR approved May 31, 2017 Project Assigned to Amaya contractor Jun 5, 2017 Kickoff tramitology Dec 15, 2017 Construction permit received Dec 20, 2017 Kickoff civil works Mar 14, 2018 Local Goverment Inspection (INVEA) Mar 22, 2018 Stopped Construction with stamped seals in building Mar 23, 2018 Seal removed by Local Municipality Office Apr 2, 2018 Construction closure re-stamped seals in Facility Apr 4, 2018 Stamped seal response to Authority (By ASM) Apr 11, 2018 Fines payment by stamping seals & construction closure (By ASM) Apr 20, 2018 Appearance of the legal representative Apr 23, 2018 Construction Permit validation by Municipality Office Apr 25, 2018 Seal removed by Local Municipality Office May 29, 2018 Construction process stopped Jun 18, 2018 Facility closure by INVEA Inspectors The Facility was closed, due the construction process in facility Dec 1, 2018 Project re-assigned to MIRMISA contractor