CPG consults with WASA on BWRPIn August 2012, CPG, in collaboration with PUB Consultants Pte Ltd, through an MOU signed between PUB and WASA, was commissioned by WASA to undertake a technical study and concept design for the Beetham Water Reuse Project. The objective was to study the feasibility and develop a technical concept design for a water recycling plant that will convert the treated effluent from BWWTP into high grade industrial process water for supply to industrial users. CPG and KPMG Singapore prepare RFP
-
-
NOTICE OF TENDER for Design & Build, and Operation & Maintenance of the Beetham Water Recycling Plant published on 2 September 2013 by NGC
-
The budget statement is delivered by Minister of Finance & the Economy, Sen Larry Howai, with no mention of the Billion-Dollar BWRP, the RFP for which was published a mere seven days prior.
-
The Minister of the Environment & Water Resources, makes a formal statement detailing the expansion of Desalcott’s daily output from 32 million to 40 million gallons.
-
BWRP contract was awarded to SIS Ltd and its subcontractors in the sum of $1.043 Billion.
-
WASA announces that Desalcott’s expansion programme is delayed and will take effect in April, instead of January as originally anticipated.
Statement from WASA