Construction Timeline By julialeedavis May 3, 2010 Recieve Notice to Proceed with Construction Period: May 3, 2010 to May 7, 2010 Engineer Set Grading Limits Period: May 3, 2010 to May 14, 2010 Demolish Concrete Pads Period: May 17, 2010 to Jun 11, 2010 Excavate Building Pad Jun 9, 2010 Insight Park Breaks Ground Period: Jun 14, 2010 to Jun 18, 2010 Vibro Stone Columns Period: Jun 21, 2010 to Jun 25, 2010 Spread Footings East Wing Period: Jun 23, 2010 to Jun 29, 2010 Spread Footings Central Period: Jun 23, 2010 to Jun 29, 2010 Spread Footings West Wing Period: Jun 29, 2010 to Jul 1, 2010 Underslab Plumbing East Wing Period: Jun 29, 2010 to Jul 8, 2010 East Wing Column Piers with Anchor Bolts Period: Jun 29, 2010 to Jul 5, 2010 Underslab Electrical Central Period: Jun 29, 2010 to Jul 26, 2010 Foundation Walls West Wing Period: Jul 1, 2010 to Sep 8, 2010 Underslab Plumbing Central Period: Jul 2, 2010 to Jul 13, 2010 Grade Beams East Wing Period: Jul 6, 2010 to Jul 23, 2010 Underslab Electrical West Wing Period: Jul 8, 2010 to Aug 9, 2010 Underslab Plumbing West Wing Period: Jul 15, 2010 to Aug 5, 2010 West Wing Column Piers with Anchor Bolts Period: Jul 15, 2010 to Jul 19, 2010 Edge Form & Fine Grade Slab East Wing Period: Jul 15, 2010 to Aug 5, 2010 Column Piers with Anchor Bolts West Wing Period: Jul 20, 2010 to Jul 21, 2010 Vapor Barrier/Reinforcing at Slab East Wing Period: Jul 21, 2010 to Aug 5, 2010 Grade Beams West Wing Period: Jul 28, 2010 to Aug 10, 2010 Erect Steel Columns East Wing Period: Jul 28, 2010 to Aug 10, 2010 Elevator Pit Period: Aug 3, 2010 to Aug 25, 2010 Erect Castellated Beams East Wing Period: Aug 12, 2010 to Aug 16, 2010 Vapor Barrier/Reinforcing at Slab West Wing Period: Aug 16, 2010 to Aug 17, 2010 Pour Slab On Grade West Period: Aug 17, 2010 to Aug 25, 2010 Install Steel Deck East Wing Period: Aug 25, 2010 to Sep 10, 2010 Column Piers with Anchor Bolts at Central Period: Aug 25, 2010 to Sep 10, 2010 Column Piers with Anchor Bolts at Central Period: Aug 25, 2010 to Sep 10, 2010 Grade Beams at Central Period: Aug 30, 2010 to Sep 3, 2010 Pour 2nd Floor Slab East Wing Period: Sep 9, 2010 to Sep 15, 2010 Erect Steel Columns West Period: Sep 9, 2010 to Sep 16, 2010 Castellated Beams West Wing Period: Sep 13, 2010 to Sep 23, 2010 Exterior Stud Framing 1st Floor at East Wing Period: Sep 17, 2010 to Sep 20, 2010 Erect Steel Columns Central Period: Sep 20, 2010 to Sep 30, 2010 Erect Castellated Beams Central Period: Sep 22, 2010 to Sep 24, 2010 Install Steel Joists East Roof Period: Sep 23, 2010 to Oct 4, 2010 Install Steel Deck West Period: Sep 27, 2010 to Oct 1, 2010 Exterior Stud Framing 2nd Floor Period: Oct 7, 2010 to Oct 12, 2010 Install Perimeter Bent Plate at East Roof Period: Oct 15, 2010 to Oct 22, 2010 Exterior Stud Framing 1st Floor Central Period: Oct 15, 2010 to Oct 22, 2010 Exterior Stud Framing 1st Floor at West Wing Period: Oct 18, 2010 to Nov 2, 2010 Install Duct Work 1st Floor East Wing Period: Oct 20, 2010 to Nov 12, 2010 Install Metal Stud Framing 1st Floor at West Wing Period: Oct 20, 2010 to Nov 12, 2010 Install Metal Stud Framing 1st Floor Central Period: Oct 25, 2010 to Oct 27, 2010 Window Blocking 1st Floor at East Wing Period: Oct 27, 2010 to Nov 18, 2010 Erect Steel Stairs Period: Oct 27, 2010 to Jan 27, 2011 Install Mechanical and Roof Opening Support Frames Period: Oct 27, 2010 to Nov 3, 2010 Window Blocking 2nd Floor at East Wing Period: Oct 27, 2010 to Nov 3, 2010 Window Blocking 1st Floor Central Period: Oct 27, 2010 to Nov 3, 2010 Window Blocking 1st Floor at West Wing Period: Oct 27, 2010 to Nov 9, 2010 Erect Beams at Central/West Roof Period: Oct 28, 2010 to Nov 4, 2010 Install Metal Stud Framing 2nd Floor East Wing Period: Nov 1, 2010 to Nov 2, 2010 Install Steel Deck Central Period: Nov 8, 2010 to Nov 15, 2010 Window Blocking 2nd Floor Central Period: Nov 8, 2010 to Nov 15, 2010 Window Blocking 2nd Floor at West Wing Period: Nov 12, 2010 to Apr 5, 2011 Install Duct Work 1st Floor Central Period: Nov 12, 2010 to Apr 5, 2011 Install Duct Work 1st Floor at West Wing Period: Nov 15, 2010 to Nov 18, 2010 Install Perimeter Bent Plate at Central/West Roof Period: Nov 18, 2010 to Nov 24, 2010 Install Metal Roof Deck Central/West Roof Period: Nov 20, 2010 to May 20, 2011 Install Windows & Curtain Wall East Wing Period: Nov 24, 2010 to May 17, 2011 Install Windows & Curtain Wall Central/West Wing Period: Nov 24, 2010 to Jan 25, 2011 Install Metal Stud Framing 2nd Floor Cent/West Wing Period: Nov 29, 2010 to Dec 10, 2010 Install Roof Drain/Penetration at Roof Deck East Period: Nov 30, 2010 to Apr 5, 2011 Install Duct Work 2nd Floor Central/West Wing Period: Nov 30, 2010 to Dec 3, 2010 Pour 2nd Floor Slab Central Period: Dec 10, 2010 to Jan 31, 2011 Install Tapered Roof Insulation & Crickets East Roof Period: Dec 14, 2010 to Dec 20, 2010 CMU Elevator Shaft 2nd to Roof Period: Dec 14, 2010 to Mar 30, 2011 Foil Face Insulation 1st Floor at East Wing Period: Dec 14, 2010 to Dec 20, 2010 Install Roof Drain/Penetration at Roof Deck West Period: Dec 14, 2010 to May 12, 2011 Install Mechanical Piping 1st Floor East Wing Period: Dec 14, 2010 to May 19, 2011 Install Mechanical Piping 1st Floor Cent/West Wing Period: Dec 14, 2010 to May 13, 2011 Install Mechanical Piping 2nd Floor East Wing Period: Dec 20, 2010 to May 19, 2011 Install Mechanical Piping 2nd Floor Central/West Wing Period: Jan 7, 2011 to Mar 28, 2011 Insulation & Drywall 1st Floor Central/West Wing Period: Jan 11, 2011 to Mar 30, 2011 Install Brick/Stone 1st Floor at East Wing Period: Jan 19, 2011 to May 27, 2011 Install Brick & Stone 2nd Floor at East Wing Period: Jan 25, 2011 to May 26, 2011 Install Lightning Protection West Roof Period: Jan 25, 2011 to May 26, 2011 Install Lightning Protection East Roof Period: Jan 28, 2011 to Feb 21, 2011 Install Heat Pumps 1st Floor East WIng Period: Jan 31, 2011 to Feb 21, 2011 Install Heat Pumps 2nd Floor East Wing Period: Feb 3, 2011 to Mar 23, 2012 Install Plumbing Equipment in Mechanical Room 1st Floor Period: Feb 10, 2011 to Feb 21, 2011 Install Heat Pumps 2nd Floor Central/West Wing Period: Feb 10, 2011 to Feb 21, 2011 Install Heat Pumps 1st Floor Central/West Wing Period: Feb 15, 2011 to May 26, 2011 Insulation & Drywall 2nd Floor Central/West Wing Period: Feb 15, 2011 to Mar 29, 2011 Insulation & Drywall 1st Floor East Wing Period: Feb 18, 2011 to May 26, 2011 Install Brick/Stone1st Floor at Central/West Wing Period: Mar 11, 2011 to May 26, 2011 Demo & Grading at Connection to Intramural Period: Mar 17, 2011 to Mar 30, 2011 Install Roof Top Mechanical Equipment Period: Mar 18, 2011 to Mar 30, 2011 Finish Drywall 1st Floor Central/West Wing Period: Mar 21, 2011 to Mar 31, 2011 Finish Drywall 1st Floor East Wing Period: Mar 21, 2011 to Mar 31, 2011 Finish Drywall 2nd Floor East Wing Period: Mar 24, 2011 to Apr 6, 2011 Insulation & Drywall 2nd Floor East Wing Period: Mar 24, 2011 to Mar 30, 2011 Install Sun Shades South Elevator East Wing Period: Mar 25, 2011 to May 25, 2011 Prime/Paint 1st Coat 1st Floor East Wing Period: Mar 25, 2011 to Apr 11, 2011 Install Sun Shades South Elevator West Wing Period: Mar 29, 2011 to Apr 4, 2011 Prime/Paint 1st Coat 2nd Floor East Wing Period: Apr 5, 2011 to Jun 16, 2011 Hang & Finish Drywall Ceilings 1st Floor Central/West Period: Apr 5, 2011 to Jun 16, 2011 Hang & Finish Drywall Ceilings 2nd Floor Central/West Period: Apr 11, 2011 to May 27, 2011 Install Elevator Beam, Rails, Ladders and Equipment Period: Apr 11, 2011 to Jun 2, 2011 Install Elevator Car Period: Apr 19, 2011 to Jun 17, 2011 Prime/Paint 1st Coat 2nd Floor Central/West Wing May 4, 2011 Hook Up Permanent Power Period: May 12, 2011 to Jun 24, 2011 Install Elevator Cab Finishes Period: May 25, 2011 to May 27, 2011 Install Louver Equipment Screen at High Roof East Period: May 25, 2011 to May 27, 2011 Install Louver Equipment Screen at High Roof West Period: May 26, 2011 to May 27, 2011 Stone Base at Connection to Intramural Period: May 27, 2011 to May 31, 2011 Install Elevator Door Frames Period: May 27, 2011 to May 31, 2011 Asphalt Paving at Connection to Intramural Period: May 31, 2011 to Jun 1, 2011 Open Temporary Road Period: Jun 20, 2011 to Jun 21, 2011 Install Doors & Hardware 1st Floor East Wing Period: Jun 20, 2011 to Jul 11, 2011 Porcalin Tile & Terrazzo 1st Floor Central/West Wing Period: Jun 20, 2011 to Jun 21, 2011 Install Doors & Hardware 2nd Floor East Wing Period: Jun 20, 2011 to Jun 29, 2011 Install Roller Shades 1st Floor Central/West Wing Period: Jun 20, 2011 to Jul 1, 2011 Install Doors and Hardware 1st Floor Central/West Wing Period: Jun 24, 2011 to Jun 30, 2011 Final Paint 1st Floor East WIng Period: Jun 24, 2011 to Jul 6, 2011 Install Roller Shades 2nd Floor Central/West Wing Period: Jul 1, 2011 to Jul 18, 2011 Demo & Grading at Connection to Hawthorne Road Period: Jul 5, 2011 to Jul 6, 2011 Install Carpet 1st Floor Central/West Wing Period: Jul 5, 2011 to Jul 11, 2011 Final Paint 2nd Floor East Wing Period: Jul 12, 2011 to Jul 25, 2011 Install Doors & Hardware 2nd Floor Central/West Wing Period: Jul 20, 2011 to Jul 22, 2011 Aspahlt Paving at Connection to Hawthorne Road Period: Jul 20, 2011 to Aug 17, 2011 Landscaping and Signage Allowance Period: Jul 22, 2011 to Jul 29, 2011 Traffic Striping and Signage at Connections Jul 29, 2011 Open New Intrmural Road Period: Aug 8, 2011 to Aug 15, 2011 Final HVAC Start Up with Geothermal Period: Aug 15, 2011 to Aug 29, 2011 Final Commissioning/Test Ballance Period: Sep 1, 2011 to Sep 14, 2011 Final Inspections/Punchlist Sep 14, 2011 Building Substantially Complete Jan 2, 2012 Insight Park Opens 1st Building Apr 5, 2012 Grand Opening of Insight Park