Construction Timeline

  • Recieve Notice to Proceed with Construction

  • Period: to

    Engineer Set Grading Limits

  • Period: to

    Demolish Concrete Pads

  • Period: to

    Excavate Building Pad

  • Insight Park Breaks Ground

  • Period: to

    Vibro Stone Columns

  • Period: to

    Spread Footings East Wing

  • Period: to

    Spread Footings Central

  • Period: to

    Spread Footings West Wing

  • Period: to

    Underslab Plumbing East Wing

  • Period: to

    East Wing Column Piers with Anchor Bolts

  • Period: to

    Underslab Electrical Central

  • Period: to

    Foundation Walls West Wing

  • Period: to

    Underslab Plumbing Central

  • Period: to

    Grade Beams East Wing

  • Period: to

    Underslab Electrical West Wing

  • Period: to

    Underslab Plumbing West Wing

  • Period: to

    West Wing Column Piers with Anchor Bolts

  • Period: to

    Edge Form & Fine Grade Slab East Wing

  • Period: to

    Column Piers with Anchor Bolts West Wing

  • Period: to

    Vapor Barrier/Reinforcing at Slab East Wing

  • Period: to

    Grade Beams West Wing

  • Period: to

    Erect Steel Columns East Wing

  • Period: to

    Elevator Pit

  • Period: to

    Erect Castellated Beams East Wing

  • Period: to

    Vapor Barrier/Reinforcing at Slab West Wing

  • Period: to

    Pour Slab On Grade West

  • Period: to

    Install Steel Deck East Wing

  • Period: to

    Column Piers with Anchor Bolts at Central

  • Period: to

    Column Piers with Anchor Bolts at Central

  • Period: to

    Grade Beams at Central

  • Period: to

    Pour 2nd Floor Slab East Wing

  • Period: to

    Erect Steel Columns West

  • Period: to

    Castellated Beams West Wing

  • Period: to

    Exterior Stud Framing 1st Floor at East Wing

  • Period: to

    Erect Steel Columns Central

  • Period: to

    Erect Castellated Beams Central

  • Period: to

    Install Steel Joists East Roof

  • Period: to

    Install Steel Deck West

  • Period: to

    Exterior Stud Framing 2nd Floor

  • Period: to

    Install Perimeter Bent Plate at East Roof

  • Period: to

    Exterior Stud Framing 1st Floor Central

  • Period: to

    Exterior Stud Framing 1st Floor at West Wing

  • Period: to

    Install Duct Work 1st Floor East Wing

  • Period: to

    Install Metal Stud Framing 1st Floor at West Wing

  • Period: to

    Install Metal Stud Framing 1st Floor Central

  • Period: to

    Window Blocking 1st Floor at East Wing

  • Period: to

    Erect Steel Stairs

  • Period: to

    Install Mechanical and Roof Opening Support Frames

  • Period: to

    Window Blocking 2nd Floor at East Wing

  • Period: to

    Window Blocking 1st Floor Central

  • Period: to

    Window Blocking 1st Floor at West Wing

  • Period: to

    Erect Beams at Central/West Roof

  • Period: to

    Install Metal Stud Framing 2nd Floor East Wing

  • Period: to

    Install Steel Deck Central

  • Period: to

    Window Blocking 2nd Floor Central

  • Period: to

    Window Blocking 2nd Floor at West Wing

  • Period: to

    Install Duct Work 1st Floor Central

  • Period: to

    Install Duct Work 1st Floor at West Wing

  • Period: to

    Install Perimeter Bent Plate at Central/West Roof

  • Period: to

    Install Metal Roof Deck Central/West Roof

  • Period: to

    Install Windows & Curtain Wall East Wing

  • Period: to

    Install Windows & Curtain Wall Central/West Wing

  • Period: to

    Install Metal Stud Framing 2nd Floor Cent/West Wing

  • Period: to

    Install Roof Drain/Penetration at Roof Deck East

  • Period: to

    Install Duct Work 2nd Floor Central/West Wing

  • Period: to

    Pour 2nd Floor Slab Central

  • Period: to

    Install Tapered Roof Insulation & Crickets East Roof

  • Period: to

    CMU Elevator Shaft 2nd to Roof

  • Period: to

    Foil Face Insulation 1st Floor at East Wing

  • Period: to

    Install Roof Drain/Penetration at Roof Deck West

  • Period: to

    Install Mechanical Piping 1st Floor East Wing

  • Period: to

    Install Mechanical Piping 1st Floor Cent/West Wing

  • Period: to

    Install Mechanical Piping 2nd Floor East Wing

  • Period: to

    Install Mechanical Piping 2nd Floor Central/West Wing

  • Period: to

    Insulation & Drywall 1st Floor Central/West Wing

  • Period: to

    Install Brick/Stone 1st Floor at East Wing

  • Period: to

    Install Brick & Stone 2nd Floor at East Wing

  • Period: to

    Install Lightning Protection West Roof

  • Period: to

    Install Lightning Protection East Roof

  • Period: to

    Install Heat Pumps 1st Floor East WIng

  • Period: to

    Install Heat Pumps 2nd Floor East Wing

  • Period: to

    Install Plumbing Equipment in Mechanical Room 1st Floor

  • Period: to

    Install Heat Pumps 2nd Floor Central/West Wing

  • Period: to

    Install Heat Pumps 1st Floor Central/West Wing

  • Period: to

    Insulation & Drywall 2nd Floor Central/West Wing

  • Period: to

    Insulation & Drywall 1st Floor East Wing

  • Period: to

    Install Brick/Stone1st Floor at Central/West Wing

  • Period: to

    Demo & Grading at Connection to Intramural

  • Period: to

    Install Roof Top Mechanical Equipment

  • Period: to

    Finish Drywall 1st Floor Central/West Wing

  • Period: to

    Finish Drywall 1st Floor East Wing

  • Period: to

    Finish Drywall 2nd Floor East Wing

  • Period: to

    Insulation & Drywall 2nd Floor East Wing

  • Period: to

    Install Sun Shades South Elevator East Wing

  • Period: to

    Prime/Paint 1st Coat 1st Floor East Wing

  • Period: to

    Install Sun Shades South Elevator West Wing

  • Period: to

    Prime/Paint 1st Coat 2nd Floor East Wing

  • Period: to

    Hang & Finish Drywall Ceilings 1st Floor Central/West

  • Period: to

    Hang & Finish Drywall Ceilings 2nd Floor Central/West

  • Period: to

    Install Elevator Beam, Rails, Ladders and Equipment

  • Period: to

    Install Elevator Car

  • Period: to

    Prime/Paint 1st Coat 2nd Floor Central/West Wing

  • Hook Up Permanent Power

  • Period: to

    Install Elevator Cab Finishes

  • Period: to

    Install Louver Equipment Screen at High Roof East

  • Period: to

    Install Louver Equipment Screen at High Roof West

  • Period: to

    Stone Base at Connection to Intramural

  • Period: to

    Install Elevator Door Frames

  • Period: to

    Asphalt Paving at Connection to Intramural

  • Period: to

    Open Temporary Road

  • Period: to

    Install Doors & Hardware 1st Floor East Wing

  • Period: to

    Porcalin Tile & Terrazzo 1st Floor Central/West Wing

  • Period: to

    Install Doors & Hardware 2nd Floor East Wing

  • Period: to

    Install Roller Shades 1st Floor Central/West Wing

  • Period: to

    Install Doors and Hardware 1st Floor Central/West Wing

  • Period: to

    Final Paint 1st Floor East WIng

  • Period: to

    Install Roller Shades 2nd Floor Central/West Wing

  • Period: to

    Demo & Grading at Connection to Hawthorne Road

  • Period: to

    Install Carpet 1st Floor Central/West Wing

  • Period: to

    Final Paint 2nd Floor East Wing

  • Period: to

    Install Doors & Hardware 2nd Floor Central/West Wing

  • Period: to

    Aspahlt Paving at Connection to Hawthorne Road

  • Period: to

    Landscaping and Signage Allowance

  • Period: to

    Traffic Striping and Signage at Connections

  • Open New Intrmural Road

  • Period: to

    Final HVAC Start Up with Geothermal

  • Period: to

    Final Commissioning/Test Ballance

  • Period: to

    Final Inspections/Punchlist

  • Building Substantially Complete

  • Insight Park Opens 1st Building

  • Grand Opening of Insight Park