Initial renovations for the library, paid for by funding from the State Universty Construction Fund, commence with interiror renovations planned for the following winter.
-
-
$36,745,000 allocated to SUNY via State Universtiy Contruction Fund in order "to address student needs and allow Wooster to serve as a multi-use building by housing a combination of academic departments, administrative offices and food venues."
http://oracle.newpaltz.edu/wooster-renovations-remain-on-track/ -
-
-
“The State University Construction Fund (SUCF), in consultation with the College administration, terminated, for convenience, its contract with the original general contractor for the project,” John Mc Enrue, director of facilities design and construction, said.
http://oracle.newpaltz.edu/library-construction-suspended/ -
-
Due to state financing issues, SUNY-wide construction is delayed for a series of months.
http://oracle.newpaltz.edu/construction-projects-delayed-by-state/ -
Though funding was secured in 2008, "the timing and financial situation wasn't the best so it was put off til now."
http://oracle.newpaltz.edu/library-renovations-on-the-horizon/ -