-
River Crossing Study is performed indentifying the composition of three bore holes in the proposed area of the Rianila River HDD (HOC 8)
-
Parties enter into contracts
-
Meetings held in Toronto from 7/30 to 7/31 to clarify responsibilities of the parties
-
SLI issues Geotechnical Prospective Report to CCG, informing it of presence of rock at HDD 2 and HDD 3
-
SLI issues borehole date in relation to HDD 3 (HOC 3)
-
SLI issues ECN 43 regarding extension of 36" HDPE pipe (HOC 15)
-
New completion date set for 9/30/2009; payment made to resolve CCG's claims
-
SLI confirms that quantities of erosion control beyond those found in the bid proposal will be paid at the Contract (HOC 1.3)
-
SLI issues ECN regarding potential change in the distribution line (HOC 13)
-
Restrictions in place on access to TMFroad from June through September (HOC 7)
-
Contract converted to lumpsum; all claims released; time for completion revised to 12/31/209;established requirement of tranche payments if CC and MC reached by 12/31/2009 and 3/31/2010 (HOC 4)
-
Employee fatalityt occurs on Tailings Road (HOC 5)
-
SLI suspends work due to 7/2/2009 fatality (on all locations other than Tailings Road, suspension ends 7/9/2009) (HOC 5)
-
SLI suspends work due to 7/2/2009 fatality (on all locations other than Tailings Road, suspension ends 7/9/2009) (HOC 5)
-
SLI expresses intent to apply back charges incurred prior to signing of MOU 2 (HOC 2)
-
SLI issues drawing confirming that Shatandra River crossing is to be performed by open-cut method (HOC 14)
-
CCG informs SLI that it views the incorporation of pre-MOU 2 backcharges to be a violation of MOU 2 (HOC 2)
-
CCG performs work on Vakona Road (HOC 16)
-
Floating bridge at AR10 inaccessible due to rain (HOC 10)
-
CCG revieves verbal request to return Vakona Road to equal or better condition than when work started (HOC 16)
-
SLI suspends work due to lack of ambulance coverage (HOC 5)
-
Access prevented by locals at AR2 (HOC 12)
-
CCG advises SLI that unexpected hard rock has been encountered at HDD 3 (HOC 3)
-
SLI issues formal instruction regarding change to the distribution line (HOC 13)
-
Access prevented by locals at AR7 (HOC 12)
-
CCG performs 14 km of reinstatement (KP 0-12, 16-18) purusant to October 2009 design drawings, which must subsequently be re-worked following 12/15/2009 design changes
-
Floating bridge at AR10 inaccessible due to rain (HOC 10)
-
SLIinforms CCG that costs associated with changes to the distribution line were included within the MOU 2 lump sum price
-
Floating Bridge at AR10 inaccessible due to rain (HOC 10)
-
SLI instructs CCG to plant vetiver grass as permanent re-vegetation measure on ROW slopes (HOC 1.1)
-
Floating bridge at AR10 inaccessible due to rain (HOC 10)
-
SLI provides design showing significant re-profiling of the ROW (HOC 1.2)
-
Hydrotesting failure occurs along Section 8 of the slurry pipeline (KP 82-KP94) (HOC 11)
-
Delays occur from AR7-AR9 due to hydrotesting failure
-
CCG informs SLI that SLI's choice of open-cut method for the Sahatandra River crossing has resulted in delay (HOC 14)
-
CCG requests change order relating to re-vegitation of ROW (HOC 1.1)
-
CCG suffers damage and delay due to exceptionally adverse weather (HOC 1.3)
-
CCG suffers damage and delay due to exceptionally adverse weather (HOC 9)
-
Floating bridge at AR10 inaccessible due to rain (HOC 10)
-
Access prevented by locals at KP77 (HOC 12)
-
Unforeseeable rock conditions encountered at KP 43 (HOC 6)
-
CCG suffers damage and delay due to exceptionally adverse weather (HOC 9)
-
CCG performs seeding trial at KP 2+500
-
Access prevented by locals at KP77 (HOC 12)
-
CCG perfroms manual seeding between the mine and AR2 (HOC 1.1)
-
CCG states belief that costs of reinstatement and re-vegetation were not included within MOU 2 lump sum price (HOC 1.1;1.2)
-
Access prevented by locals at KP 85-KP 91 (HOC 12)
-
Unforeseeable physical conditions first encountered at Rianila River crossing (HOC 8)
-
Access prevented by locals at KP118 (HOC 12)
-
SLI expresses dispproval of CCG's manual seeding and informs CCG it has contracted a hydroseeder (HOC 1.1)
-
CCG requests change order relating to re-profiling of ROW (HOC 1.2)
-
CCG asserts it is entitled to both tranch payments, as delays were beyond its control (HOC 4)
-
Access prevented by locals at KP105 (HOC 12)
-
Access prevented by locals at KP 105 (HOC 12)
-
Unforeseeale rock conditions encountered at KP 77 (HOC 6)
-
Unforeseeable rock conditions encountered at KP 104 (HOC 6)
-
HOC 4
-
CCG informs SLI that hydroseeding was performed at KP 7-10 only two days after manual seeding was performed, and thus CCG should not be liable for a backcharge for this hydroseeding (HOC 1.1)
-
Hydrotesting failure occurs along Section 5 (KP 44-KP-52) of the Slurry pipeline
-
Delays occur from KP 44-KP 52 due to hydrotesting failure (HOC 11)
-
Access prevented by locals at AR9 (HOC 12)
-
SLI informs CCG that its previous failed attempts at manual seeding are negaively affecting hydroseeding, such as at KP 9-10 (HOC 1.1)
-
ESSAR informs CCG that Rianila River works are complete (HOC 8)
-
Access prevented by locals at SLI Site Plant (HOC 12)
-
CCG informs SLI that it will not achieve construction completion by date required for tranche payment (12/31), but asserts the reasons were beyond its control (HOC 4)