Calendrier By melymelo76 Period: May 1, 2011 to Jul 15, 2011 Phase 1 Period: May 1, 2011 to May 15, 2011 Programme Progamme Period: May 15, 2011 to Jun 4, 2011 Esquisse Jun 1, 2011 Estimatif Period: Jun 4, 2011 to Jul 15, 2011 Mise au point projet Jul 15, 2011 Mise au point contrat Phase 2 Period: Jul 15, 2011 to Aug 30, 2011 Phase 2 Period: Jul 17, 2011 to Oct 15, 2011 Conception-élaboration PC Period: Oct 15, 2011 to Jan 20, 2012 Instruction PC Period: Jan 20, 2012 to Mar 31, 2013 Phase 3 Period: Jan 30, 2012 to Feb 15, 2012 Contrat Conception Construction Feb 1, 2012 Arrêté PC Period: Feb 1, 2012 to Apr 25, 2012 Recours des Tiers Period: Feb 15, 2012 to Apr 4, 2012 Préparation Period: Apr 4, 2012 to Apr 20, 2012 Démolition Period: Apr 20, 2012 to Jan 30, 2013 Construction Period: Jan 1, 2013 to Feb 25, 2013 Emménagement équipement Feb 25, 2013 Réception