18015 Ph 2 - Construction By 18015 Felimo Ph 2 Period: Nov 30, 2020 to Jan 25, 2021 Work preparation Jan 19, 2021 Mobilisation Period: Feb 9, 2021 to Apr 15, 2021 Energieweg Period: Feb 9, 2021 to Mar 15, 2021 Langeweg drilling Period: Feb 16, 2021 to Apr 20, 2021 Langeweg open trench Period: Mar 15, 2021 to May 20, 2021 HDD Period: May 3, 2021 to Jun 1, 2021 Open trench HDD to LSNed Period: May 27, 2021 to Jun 17, 2021 Testing, cleaning, drying Jun 25, 2021 Completion of works