Zona 6 By monikmarino Period: Sep 12, 2012 to Sep 29, 2012 Traslados Sacsa para entrega de zona Period: Sep 29, 2012 to Oct 5, 2012 Cerramiento y señalización Period: Oct 5, 2012 to Oct 30, 2012 Muros drywall Period: Oct 5, 2012 to Nov 14, 2012 Carpintería metálica Period: Oct 9, 2012 to Oct 31, 2012 Estructura concreto Period: Oct 10, 2012 to Oct 20, 2012 Demoliciones y retiros Period: Oct 11, 2012 to Oct 27, 2012 Mampostería Period: Oct 17, 2012 to Oct 31, 2012 Desmontes Period: Oct 17, 2012 to Nov 16, 2012 Cielo raso Period: Oct 26, 2012 to Nov 13, 2012 Mesones Period: Oct 31, 2012 to Nov 20, 2012 Pisos y plantillas Period: Nov 1, 2012 to Nov 13, 2012 Instalaciones Period: Nov 1, 2012 to Nov 14, 2012 Carpintería en madera Period: Nov 7, 2012 to Nov 14, 2012 Instalaciones baños Period: Nov 14, 2012 to Nov 15, 2012 Divisiones Period: Nov 15, 2012 to Nov 17, 2012 Espejos Nov 22, 2012 Recepción de zona