Zona 5 By monikmarino Period: Sep 12, 2012 to Sep 29, 2012 Traslados SACSA para entrega de Zona Period: Sep 29, 2012 to Oct 10, 2012 Cerramiento y señalización Period: Oct 5, 2012 to Oct 10, 2012 Desmontes Period: Oct 5, 2012 to Dec 17, 2012 Estructuras de concreto Period: Oct 5, 2012 to Nov 24, 2012 Instalaciones Period: Oct 5, 2012 to Dec 7, 2012 Cielo raso Period: Oct 10, 2012 to Nov 14, 2012 Demoliciones y retiros Period: Oct 12, 2012 to Dec 20, 2012 Ascensores Period: Oct 22, 2012 to Nov 15, 2012 Mampostería Period: Oct 22, 2012 to Dec 21, 2012 Pisos y plantillas Period: Nov 3, 2012 to Nov 19, 2012 Muros Drywall Period: Nov 24, 2012 to Dec 13, 2012 Instalaciones de enchape Baños y aparatos Period: Dec 1, 2012 to Dec 4, 2012 Mesones Period: Dec 13, 2012 to Dec 18, 2012 Divisiones en acero inoxidable Period: Dec 18, 2012 to Dec 20, 2012 Espejos Period: Dec 18, 2012 to Dec 20, 2012 Carpintería Period: Dec 20, 2012 to Dec 29, 2012 Estuco y Pintura Period: Dec 29, 2012 to Jan 10, 2013 Toma de detalles Jan 10, 2013 Recepción de zona por parte de SACSA