PROGRAMACION By jefferson parada marin Period: Dec 3, 2018 to Mar 30, 2019 "FASE 1 - PLACAS EN DRYWALL COMPLETAS ESTRUCTURA Y 1 LAMINA DE DRYWALL EN MUROS " Period: Dec 17, 2018 to Apr 13, 2019 instalacion puntos electricos, aire acondicionado y desague de aires acondicionados Period: Dec 24, 2018 to Apr 20, 2019 FASE 2 - pasta - dilataciones - estuco- primeriada Period: Jan 7, 2019 to May 4, 2019 Enchape Period: Feb 11, 2019 to May 11, 2019 aluminio Period: Feb 18, 2019 to May 18, 2019 madera (2 pisos semanales) Period: Feb 18, 2019 to Mar 23, 2019 lavaderos Period: Feb 25, 2019 to May 25, 2019 mesones (2 pisos semanales) Period: Apr 1, 2019 to May 25, 2019 suicheria, lamparas y tableros