Courier Service Project Communication & Pilot Timeline

By sklein
  • Period: to

    Mention Courier Changes During Check 21 Refreshers

  • Present Pilot Plan @ Supervisor Meeting (NER & CIAR)

  • Present Pilot Plan @ Supervisor Meeting (ECR)

  • Present Pilot Plan @ Department Manager's Meeting

  • Send Email to Grp CUStaff Explaining Pilot

  • Notify Priority of Cancellation of Contract

  • Send Email to Grp CUStaff Notifying of Switch to Benjamin's Courier Express

  • Period: to

    Mention Courier Changes During Savings Bonds Topic @ May PK's

  • Send Reminder Email to Grp CUStaff Reviewing Upcoming Pilot

  • Equip All Branches w/ Scanning & Emailing Capabilities

  • Period: to

    Conduct 2 Days/Week Pilot (All Documents Except Real Estate)

  • Period: to

    Mention Courier Changes During Foreign Currency Training

  • Finish Development of New Home Equity Processes

  • Period: to

    Conduct Home Equity Pilot

  • Period: to

    Train Loan Staff on New Home Equity Processes

  • Courier Schedule Reduction Go/No Go Date

  • Transition From Priority Express to Benjamin's Courier Express