Figure 4: Timeline for DHL EV Project

By jollies
  • Period: to

    Define Objectives

    Set 60% electrification and 25% emission reduction goals.
  • Period: to

    Conduct Feasibility Study

    Analyze costs, infrastructure, and grid impact.
  • Period: to

    Secure Stakeholder Approval

    Obtain approval from DHL and local authorities.
  • Period: to

    Purchase 60 VW ID.Buzz Cargo Vans

    Negotiate and order 60 electric vans.
  • Period: to

    Source Charging Station Equipment

    Identify suppliers and order 10 charging stations.
  • Period: to

    Contract Suppliers for Maintenance

    Select and contract maintenance providers.
  • Period: to

    Install Charging Stations

    Install 10 stations in Sandton and Midrand.
  • Period: to

    Upgrade Electrical Grid Connections

    Collaborate with Eskom for grid upgrades.
  • Period: to

    Roll Out Phase 1 (20 Vans)

    Initial rollout of 20 electric vans.
  • Period: to

    Test Charging Infrastructure

    Test charging capacity and resolve issues.
  • Period: to

    Train Drivers on EV Operation

    Train 60 drivers on safety and efficiency.
  • Period: to

    Monitor EV Performance

    Track mileage and battery health of vans.
  • Period: to

    Evaluate Cost Performance

    Quarterly EVM assessments.
  • Period: to

    Track Carbon Emissions

    Monitor emission reductions toward 25% target.
  • Period: to

    Develop Delivery Schedules

    Map and optimize routes for Sandton and Midrand.
  • Period: to

    Roll Out Phase 2 (20 Vans)

    Second rollout of 20 electric vans.
  • Period: to

    Roll Out Phase 3 (20 Vans)

    Final rollout of 20 electric vans.
  • Period: to

    Document Lessons Learned

    Compile challenges and successes.
  • Period: to

    Finalize Project Report

    Summarize outcomes for DHL leadership.
  • Period: to

    Celebrate Milestone

    Celebrate 60% electrification achievement.